Most building projects move through four design phases: schematic design (SD), design development (DD), construction documents (CD) and construction administration (CA), often with a bidding step between CD and CA. Each phase ends with a deliverable and a client approval. Naming those two things up front is how a firm keeps scope, schedule and client expectations aligned.
Why phases matter to the business, not just the design
Phases are how a firm turns a project into steps a client can approve and pay for. When a client signs off on schematic design, they are saying "yes, this is the direction." When that approval is clear and written, later changes become a conversation about additional services, not a fight about what was "included."
The trouble starts when phases are fuzzy. A client keeps reopening layout decisions during construction documents. A PM can't tell whether the team is in DD or already drawing CDs. The fee was split by phase in the proposal, but nobody checks progress against it. Clear phase names, deliverables and approvals fix most of that.
The phases, with engineering examples
Schematic design (SD): agree on the direction. The team explores options and settles the big moves: site layout, building footprint, structural system concept, major systems. For a civil engineer on a site project, SD might be a concept site plan showing building pad, access points, parking and a first look at stormwater approach. Deliverable: concept drawings and a rough cost estimate. Client action: approve one direction in writing.
Design development (DD): lock the major decisions. The approved concept gets real dimensions and real systems. Structural picks the framing system and sizes key members. MEP selects major equipment and routes main runs. Civil develops grading and drainage. Deliverable: coordinated drawings across disciplines, outline specifications and an updated cost estimate. Client action: approve the design and confirm the budget still holds.
Construction documents (CD): produce what gets permitted and built. The team completes the drawings and specifications a contractor will price and build from, and that the building department will review. Many owners ask for interim submittals (for example at 50% and 100%) so they can review before the set is final. Deliverable: the permit and bid set, signed and sealed. Client action: approve the set for permit and bidding.
Bidding or negotiation: help the owner pick a contractor. The firm answers contractor questions, issues addenda and helps the owner compare bids. Not every project has a formal bid, but most have some version of this step.
Construction administration (CA): stay with the project in the field. The firm reviews submittals and shop drawings, answers requests for information (RFIs), visits the site and reviews pay applications, depending on the contract. Deliverable: documented responses and field reports. Client action: approve change orders before the extra work starts.
Schematic design vs design development
This is the most searched pair, and the most confused one. Schematic design answers "what are we building and roughly how?" Design development answers "exactly which systems, and do they fit together?" A useful client test: if a change would move walls, columns or the site layout, it belongs in SD. If it changes equipment, sizes or materials inside an agreed layout, it belongs in DD. Changes after DD approval usually cost more because they ripple through every discipline's drawings.