Architecture Design Phases: SD, DD, CD and CA Explained

Schematic design, design development, construction documents and construction administration, explained with engineering examples for Florida firms.

A&E Operations

In short

  • Most projects move through schematic design, design development, construction documents and construction administration.
  • Each phase ends with a deliverable and a written client approval.
  • Changes after DD approval usually cost more because they ripple through every discipline.
  • In Florida, final documents filed for public record must be signed, dated and sealed under s.471.025.
On this page
  1. Why phases matter to the business, not just the design
  2. The phases, with engineering examples
  3. Schematic design vs design development
  4. Three phase mistakes that cost firms money
  5. The Florida angle
  6. Where to start
  7. Where Blueprint fits

Most building projects move through four design phases: schematic design (SD), design development (DD), construction documents (CD) and construction administration (CA), often with a bidding step between CD and CA. Each phase ends with a deliverable and a client approval. Naming those two things up front is how a firm keeps scope, schedule and client expectations aligned.

Why phases matter to the business, not just the design

Phases are how a firm turns a project into steps a client can approve and pay for. When a client signs off on schematic design, they are saying "yes, this is the direction." When that approval is clear and written, later changes become a conversation about additional services, not a fight about what was "included."

The trouble starts when phases are fuzzy. A client keeps reopening layout decisions during construction documents. A PM can't tell whether the team is in DD or already drawing CDs. The fee was split by phase in the proposal, but nobody checks progress against it. Clear phase names, deliverables and approvals fix most of that.

The phases, with engineering examples

Schematic design (SD): agree on the direction. The team explores options and settles the big moves: site layout, building footprint, structural system concept, major systems. For a civil engineer on a site project, SD might be a concept site plan showing building pad, access points, parking and a first look at stormwater approach. Deliverable: concept drawings and a rough cost estimate. Client action: approve one direction in writing.

Design development (DD): lock the major decisions. The approved concept gets real dimensions and real systems. Structural picks the framing system and sizes key members. MEP selects major equipment and routes main runs. Civil develops grading and drainage. Deliverable: coordinated drawings across disciplines, outline specifications and an updated cost estimate. Client action: approve the design and confirm the budget still holds.

Construction documents (CD): produce what gets permitted and built. The team completes the drawings and specifications a contractor will price and build from, and that the building department will review. Many owners ask for interim submittals (for example at 50% and 100%) so they can review before the set is final. Deliverable: the permit and bid set, signed and sealed. Client action: approve the set for permit and bidding.

Bidding or negotiation: help the owner pick a contractor. The firm answers contractor questions, issues addenda and helps the owner compare bids. Not every project has a formal bid, but most have some version of this step.

Construction administration (CA): stay with the project in the field. The firm reviews submittals and shop drawings, answers requests for information (RFIs), visits the site and reviews pay applications, depending on the contract. Deliverable: documented responses and field reports. Client action: approve change orders before the extra work starts.

Schematic design vs design development

This is the most searched pair, and the most confused one. Schematic design answers "what are we building and roughly how?" Design development answers "exactly which systems, and do they fit together?" A useful client test: if a change would move walls, columns or the site layout, it belongs in SD. If it changes equipment, sizes or materials inside an agreed layout, it belongs in DD. Changes after DD approval usually cost more because they ripple through every discipline's drawings.

Three phase mistakes that cost firms money

Starting the next phase without a written approval. A verbal "looks good" in a meeting is not an approval. Send a short email after each phase review that names the deliverable, the date and the decision, and ask the client to reply "approved."

Letting disciplines move at different phases. If architecture is in CD while MEP is still making DD decisions, the coordination problems land in the permit set. Agree on a phase gate for all disciplines, even when one team is ahead.

Not tying additional services to phases. When a client asks to revisit an approved SD layout during CD, that is a change to approved work. Write it up as an additional services request before the team redraws anything.

The Florida angle

Public owners in Florida often write their phases into their own standards. Florida Atlantic University's Professional Services Guide (April 2003 edition, the one posted on its site) lists conceptual and advanced schematic design, design development, construction documents at 50% and 100%, bidding and construction administration. It asks the owner to "Review and approve design documents at each phase of development," and requires "A cost estimate and space analysis correlated to the program requirements and approved budgets" at schematic design. If you work for a public owner, read its guide before you write your proposal: your phases and deliverables should use its names.

At the end of CD, Florida law sets the signature rule. Under Florida Statutes s.471.025 (2026 text), "All final drawings, specifications, plans, reports, or documents prepared or issued by the licensee and being filed for public record" must be "signed by the licensee, dated, and sealed." Build seal and signature time into the CD schedule, especially when several disciplines sign the same set.

Public selections also start before SD. If the project came through a CCNA selection, the scope and phases you negotiate after ranking set the frame for everything above.

Where to start

One small, safe step: take one active project and write a one-page phase map. For each phase, write three lines: the deliverable, the client approval that closes it, and the date. Share it with the client at the next meeting and ask them to confirm. You'll find out fast whether you and the client agree on where the project stands.

Where Blueprint fits

We built Blueprint to run our own engineering firm. Each firm defines its own project phases, and every project keeps its disciplines, permits, tasks, files and change orders in one record, with a client portal where the client follows progress.

Frequently asked questions

What are the phases of architectural design?

Typically schematic design, design development, construction documents, bidding or negotiation, and construction administration. Some owners add a pre-design or programming phase at the start.

What is the difference between schematic design and design development?

SD sets the direction and layout. DD locks the systems, sizes and materials inside that layout and coordinates the disciplines.

How are fees split across design phases?

It depends on the contract, project type and owner. Agree the split in the proposal and tie each payment to the client approval that closes the phase.

What happens in construction administration?

The design team reviews submittals, answers RFIs, visits the site and reviews change orders and pay applications, as the contract defines.

About the author

Camila Duarte

Digital Strategist

Digital Strategist at Sourcy. I listen to what agency owners and engineering and convert the into practical information they could use for their business.

Get new Sourcy articles in your inbox

At most one email a week: practical AI for insurance, architecture & engineering, and construction teams. No spam.

By subscribing you agree to receive the Sourcy Blog newsletter. Unsubscribe anytime. See our Privacy Policy.

Want this working in your business?

We map one workflow with your team, implement it and stay with you until it runs in production.

Get a quote
Text us, send documents, photos or videos